|
Week of Oct. 6-12, 2008
The
following is a summary of Sarasota County construction, repair
and maintenance projects that are expected to have an impact on
local traffic. This summary includes all
road or lane closures approved by the county engineer.
For more information about county construction projects and road
and lane closures, call the Sarasota County Call Center at
941-861-5000. At this site, you also can find the current status
of state roadway projects in Sarasota County in the weekly
RoadWatch Update issued by the Florida Department of
Transportation.
Swift and Proctor road intersection, Sarasota:
Construction continues on the intersection of
Swift and Proctor roads. During construction, there will be lane
closures from 9 a.m.-3 p.m., and periodic night lane closures
for the installation of new signals. The intersection
improvements include the extension of the left turn lanes on
Swift Road and new signal poles. The project is targeted for
substantial completion in early November.
Fruitville Road, Sarasota (west of McIntosh Road
to east of Cattlemen Road):
Construction continues this week for the installation of
streetlights on Fruitville Road from west of McIntosh Road to
east of Cattlemen Road. Punch list items being done this week
are expected to have little or no impact on traffic. The project
is anticipated to be finished by late January 2009.
Spencer Avenue, Laurel:
Work continues this week on installing guardrail and handrail,
along with placement of asphalt, as part of the Spencer Avenue
extension project. Spencer Avenue, which now begins at U.S. 41
and ends at Valencia Street, is being extended to Church Street,
a distance of 609 feet. The extension will include two
11-foot-wide travel lanes, 2-foot-wide shoulders and a
5-foot-wide sidewalk on the south side. Other improvements
include a water main extension along the north side of Spencer
Avenue from Valencia to Church streets, and open drainage
ditches on both sides of the roadway with stormwater treatment
in the ditches. The project is targeted for completion in
November.
Bahia Vista Street, Sarasota (from Cattlemen to
McIntosh roads):
The Bahia Vista
improvement project is substantially complete. All lanes are now
open to traffic. However, there may be some temporary lane
closures this week for minor roadway work and punch list items.
Excavation of the last pond is under way. There will be trucks
entering and leaving the roadway until this pond is completed.
All the remaining work is expected to be completed by Oct. 30.
Motorists are encouraged to exercise caution when driving
through the area.
U.S.
41 and Sorrento area, Nokomis:
Construction continues this week on the U.S. 41 lift station #25
project. No lanes are expected to be closed, but motorists
should exercise caution as trucks enter and exit the highway
from Giotto Drive to Bay Street to the north. This project will
increase capacity and reliability of wastewater service. It also
will eliminate the existing pump station and replace it with a
state-of-the-art master pumping facility.
Project completion is expected in January 2009.
Little Five Points (Herald Square), Sarasota:
Construction crews will continue working this week in the
following areas on the Little Five Points (Herald Square)
stormwater improvements: Oak Street between Pineapple Avenue and
Palm Avenue is a two-way street. Due to two-way traffic, no
parking on Oak Street between Pineapple Avenue and Palm Avenue
will be allowed. Oak Street will be closed at Pineapple Avenue.
Residents and merchants can use Oak Street from Palm Avenue.
Motorists traveling southbound on Pineapple will be detoured
onto Laurel Street to Orange Avenue southbound. Businesses in
the area can still be accessed from Pineapple Avenue.
All businesses will be open in the Burns Court
and Herald Square area. Business signs are posted to direct
patrons to area businesses.
Motorists should follow posted detours and use
caution when traveling in these areas. Signs, barricades and
flagmen will be present as needed. Construction of the entire
project is expected to be completed in November.
Webber Street, Sarasota (Java Plum Avenue to
McIntosh Road):
Punch list items will be worked on throughout the project area
for the next several weeks. Construction signs and flagmen will
be present when required. The work is part of the Phillippi
Creek Septic System Replacement Program Area K project and
sidewalk and safety improvements. Access to properties and
businesses will be maintained at all times. Construction is
expected to be finished in October 2008.
Webber Street, Sarasota (McIntosh Road to
Huntington Avenue):
Mainline installation will continue this week in the Old Forest
Lakes subdivision. Affected roads will include East Forest Lakes
Drive, East Forest Lakes Drive Circle and Twilight Place. Pit
installation will take place this week on Pony Lane and East
Forest Lakes Drive. Streets reduced to one lane will have
flagmen present. The construction is part of the Phillippi Creek
Septic System Replacement Program Area K project and sidewalk
and safety improvements. Access to properties and businesses
will be maintained at all times. Specific road and lane closures
will be posted at this site weekly. Construction is expected to
be finished in June 2009.
Nokomis area: Crews this week will be working in the following
areas as part of the Nokomis Water Line project:
-
3C-West
(area is North of Colonia Lane between Riverview Drive and
River Boulevard and north to Lucile Avenue) Crews will be
off the roadway.
-
3C-North
(area is north of Lucile Avenue to Dona Way and Portia
Street west to Valencia Street; also includes Oak Tree Lane)
Crews will be off the roadway.
-
3C-East
(area is from Albee Farm Road east to Irene Street and
between Colonia Lane to Kilpatrick Road) Survey and
restoration crews will be working in the entire area.
-
3D
(area is from
Citrus Avenue south to Magnolia Avenue off U.S. 41 to the
east) Valve and Service crews will be working on Spencer
Avenue, King Street, Tangerine Street, Hamilton Street and
Valencia Street. Valve and service crews also will be
working in the area of Palmetto Road, Shell Drive and
Magnolia Avenue, all east of U.S. 41. Valve and service
crews also will be working on the west side of U.S. 41 from
Sago Lane south to Esti Drive on Avenida La Palma, Avenida
De Bahia and Avenida De La Isla.
-
U.S. 41 (area
is on the east side of U.S. 41 from Magnolia Avenue
going north to Albee Rd) Pipe and valve crews will be
working in the state right of way on this stretch of U.S. 41
in the existing construction zone of Hubbard Construction
this week.
Motorists should use caution when traveling in
these areas. Signs, barricades and flagmen will be present as
needed to maintain two-way traffic through the area.
Construction in these areas is expected to be completed in fall
2008. Other areas are targeted for completion in early 2009.
Siesta Key Village beautification, Siesta Key:
Major work for Phase 1 of the project to bury overhead utility
lines on Ocean Boulevard within the village is complete. Poles
and wires will be removed once all remaining buildings have
converted to underground service connections.
Construction of Phase 2 is under way. Phase 2
includes brick sidewalks, intersection medallions, decorative
lighting and street signs, an information gazebo and resurfacing
of Ocean Boulevard and associated side streets. Lane closures
are expected this week at the following locations: Ocean
Boulevard (Beach Road) from Tenacity Lane to Calle Miramar,
Ocean Boulevard at Calle Miramar, and Avenida Milano between
Ocean Boulevard and Calle Minorga. To bypass areas of active
construction, northbound traffic will be detoured where
necessary from Ocean Boulevard (Beach Road) to Calle de la
Siesta, then Canal Road. Westbound traffic on Avenida Milano
will be detoured to Calle Minorga, then Avenida Madera. Portions
of sidewalk where construction is active may be temporarily
closed to pedestrians during this time. The public beach access
located at Ocean Boulevard and Beach Road will be closed during
this time. Alternate walking routes are established to maintain
pedestrian traffic in areas of closed sidewalks. All business
entrances will remain accessible. Construction of Phase 2 is
segmented to minimize disruption to the entire village area.
Construction of Phase 2 is expected to last seven months. |